Edina West Condominiums
Sanitary Sewer Replacement - Project Schedule
Building 1 - Project Start Date: September 16, 2024 | 8:00 AM - 4:30 PM Working Hours
Notes:
This schedule is subject to change - please check back frequently for timeline updates
***On the day your stack is connected to the new sanitary sewer line, your water may be turned off for a portion of the day. We will do our best to minimize the time your water is off, but please plan for water being unavailable during working hours. Bathrooms are available in the Rec Center, 1st floor, and the Community Room if needed.
Prep Work
Permits
Concrete Scanning and Layout
Electrical Repairs
Week 1 (September 16 - 20)
Concrete Cutting and Removal
Initial Sewer Excavation
Week 2 (September 23 - 27)
Monday, September 23, Tie in of New Sewer to City Sewer
Afternoon Full Building Water Shutdown - Noon - 4:00 PM
Week 3 (September 30 - October 4)
Continued Replacement of Sanitary Sewer
Week 4 (October 7 - 11)
Continued Replacement of Sanitary Sewer
Week 5 (October 14 - 18)
Continued Replacement of Sanitary Sewer
Week 6 (October 21 - 25)
Pouring on Concrete and Final Cleanup
Begin Parking Cars back in Garage on October 27th