Edina West Condominiums

Sanitary Sewer Replacement - Project Schedule

Building 2 - Project Start Date: September 23, 2024 | 8:00 AM - 4:30 PM Working Hours

Notes:

  • This schedule is subject to change - please check back frequently for timeline updates

***On the day your stack is connected to the new sanitary sewer line, your water may be turned off for a portion of the day. We will do our best to minimize the time your water is off, but please plan for water to be unavailable during working hours. Bathrooms are available in the Rec Center, 1st floor, and the Community Room if needed.

  • Prep Work

    • Permits

    • Concrete Scanning and Layout

    • Electrical Repairs

  • Week 1 (September 23 - 27)

    • Please remove all cars from Garage 2 by 10 PM on 9/24

    • Concrete Cutting and Removal

    • Initial Sewer Excavation

  • Week 2 (September 30 - October 4)

    • x, October x, Tie in of New Sewer to City Sewer

      • Afternoon Full Building Water Shutdown - Noon - 4:00 PM

  • Week 3 (October 7 - 11)

    • Continued Replacement of Sanitary Sewer

  • Week 4 (October 14 - 18)

    • Continued Replacement of Sanitary Sewer

  • Week 5 (October 21 - 25)

    • Continued Replacement of Sanitary Sewer

  • Week 6 (October 28 - November 1)

    • Installation of Concrete and Final Cleanup

  • Begin Parking Cars back in Garage on November 3rd