***On the day your stack is connected to the new sanitary sewer line, your water may be turned off for a portion of the day. We will do our best to minimize the time your water is off, but please plan for water to be unavailable during working hours. Bathrooms are available in the Rec Center, 1st floor, and the Community Room if needed.
Prep Work
Permits
Concrete Scanning and Layout
Electrical Repairs
Week 1 (September 23 - 27)
Please remove all cars from Garage 2 by 10 PM on 9/24
Concrete Cutting and Removal
Initial Sewer Excavation
Week 2 (September 30 - October 4)
x, October x, Tie in of New Sewer to City Sewer
Afternoon Full Building Water Shutdown - Noon - 4:00 PM
Week 3 (October 7 - 11)
Continued Replacement of Sanitary Sewer
Week 4 (October 14 - 18)
Continued Replacement of Sanitary Sewer
Week 5 (October 21 - 25)
Continued Replacement of Sanitary Sewer
Week 6 (October 28 - November 1)
Installation of Concrete and Final Cleanup